Kmart Concrete Slab Repairs - HESC Concrete
Client: Kmart
Project: Kmart Distribution Centre, Truganina VIC
Main Contractor: CoGRI Australia Pty Ltd
Timeline: August 2025
PROJECT OVERVIEW:
Kmart’s high-throughput distribution centre in Truganina needed defective pavement slabs repaired without disrupting operations. Eifers was re-engaged to deliver sixteen patch repairs using HESC concrete, restoring structural capacity and serviceability while protecting adjacent slabs. The work was completed inside tightly controlled shutdown windows for a continuously operating facility.
Scope
Joint inspection with the client to confirm repair extents across the warehouse pavement
Double saw cut to isolate defects and prevent spalling of adjacent slabs
Careful demolition and offsite recycling of existing concrete
Edge cleaning and inspection followed by base preparation and compaction with crushed rock
Installation of two layers of dowel bars and two layers of reinforcement mesh
Supply and placement of approximately forty eight cubic metres of HESC concrete via volumetric mixers
Slump testing at pour and cylinders cast for compressive strength verification
Outcomes
Sixteen slab patches completed inside the prescribed shutdowns without operational impact
Durable repairs with verified quality results and clean interfaces to existing pavement
Continued trust from the client supported by a multi year track record. From 2023 to July 2025 Eifers has successfully delivered more than seventy off patch repairs at this site