Kmart Concrete Pavement Repairs
Client: CoGri Australia Pty Ltd
Project: Kmart Concrete Pavement Repairs
Main Contractor: Eifers Civil
Timeline: March 2025
PROJECT OVERVIEW:
Kmart required urgent concrete pavement repairs at their facility to address deteriorating sections and maintain a safe operational environment. Given the site's near 24/7 operational schedule, the project had to be completed within a tight two-day window to decrease disruption.
Scope of Works
Saw cut and demolish 250mm thick concrete pavement in 11 designated patch areas.
Excavate and compact the base with crushed rock to ensure long-term stability.
Drill and install two layers of dowel bars to reinforce structural integrity before pouring concrete. Supply and pour rapid-set concrete using volumetric mixers for efficiency and durability.
Challenges and Solutions
Working in a continuously operational environment presented several challenges:
Minimising Pavement Damage: A double saw-cut technique was employed to prevent damage to adjacent pavement, ensuring a clean and precise finish.
Operational Continuity: Close collaboration with the client allowed for seamless coordination, preventing disruptions to Kmart’s operations.
Client Feedback
Kmart has continued to trust Eifers for ongoing pavement repairs. Over 2023 and 2024, Eifers has successfully completed more than 40 patch repairs at this site, reinforcing the client’s confidence in their expertise.